2-2-3 work schedule

A 2-2-3 schedule is a 14-day work pattern of 2 days on, 2 off, 3 on, 2 off, 2 on and 3 off, so each employee works 7 days in every 14.

Written by: Rinaily BonifacioUpdated on:

What is a 2-2-3 schedule?

A 2-2-3 schedule is a 14-day work pattern in which an employee works 2 days, has 2 days off, works 3 days, then has 2 off, works 2 and has 3 off. That adds up to 7 working days in every 14, and because the second week mirrors the first, every other weekend is a three-day weekend off.

The name only counts days. Schedules, job adverts and forums write it as 2-2-3, 223, 2/2/3 or "2 2 3", and all of them mean the same cycle. Most employers run it on 12-hour shifts, and it is a common 24/7 pattern in police departments, manufacturing plants and emergency dispatch, but the cycle itself says nothing about shift length or nights. Two crews on a 2-2-3 cover one shift seven days a week; four crews cover days and nights around the clock.

In family law, "2-2-3" also names a 50/50 custody arrangement in which a child spends two days with one parent, two with the other and three with the first, swapping each week. That is the same rhythm of days, used for something else entirely, and this page only covers the work schedule.

The 2-2-3 cycle for two crews

The simplest 2-2-3 rota has two crews sharing one shift, for example a 06:00-18:00 day shift that has to run every day of the week. Crew B works exactly the days crew A has off:

Crew

Week

Mon

Tue

Wed

Thu

Fri

Sat

Sun

A

1

Work

Work

Off

Off

Work

Work

Work

B

1

Off

Off

Work

Work

Off

Off

Off

A

2

Off

Off

Work

Work

Off

Off

Off

B

2

Work

Work

Off

Off

Work

Work

Work

After week 2 the table starts again from week 1, so the full cycle is 14 days, not 28. Crew B runs the same sequence as crew A, seven days later. Each crew works 7 days in the fortnight, never more than 3 in a row, and gets Friday to Sunday off every other week.

For 24/7 cover, the same table is used twice: crews A and B on the day shift, crews C and D on the night shift. Some employers then switch the day and night crews after every cycle, which turns the rotation into a 28-day one. The cycle of working days stays 14 days long; only the shift type changes. The Pitman schedule page shows that four-crew version day by day, including the fixed and rotating variants.

2-2-3, 3-2-2-3 and 2-3-2 are one cycle

Where you start reading changes the name, not the schedule. Read crew A's row from the Monday of week 1 and you get 2-2-3-2-2-3. Start on the Friday of week 1 and the same days read 3-2-2-3-2-2, which is why some employers call it a 3-2-2-3 schedule. Start on the Wednesday of week 2 and it becomes 2-3-2-2-3-2. A contract or job advert that names one of these is describing the same 7-in-14 rota, and it helps to add the first day of the cycle so everyone counts from the same date.

2-2-3 schedule calendar: December 2026 to December 2027

A 2-2-3 calendar needs one fixed date: the day the cycle starts. In the calendar below, crew A's cycle starts on Monday 5 January 2026, which puts the start of a new cycle on Monday 4 January 2027 as well. Crew A works on these dates, and crew B works on every other date of the month:

Month

Crew A works on

Days

December 2026

2, 3, 7, 8, 11, 12, 13, 16, 17, 21, 22, 25, 26, 27, 30, 31

16

January 2027

4, 5, 8, 9, 10, 13, 14, 18, 19, 22, 23, 24, 27, 28

14

February 2027

1, 2, 5, 6, 7, 10, 11, 15, 16, 19, 20, 21, 24, 25

14

March 2027

1, 2, 5, 6, 7, 10, 11, 15, 16, 19, 20, 21, 24, 25, 29, 30

16

April 2027

2, 3, 4, 7, 8, 12, 13, 16, 17, 18, 21, 22, 26, 27, 30

15

May 2027

1, 2, 5, 6, 10, 11, 14, 15, 16, 19, 20, 24, 25, 28, 29, 30

16

June 2027

2, 3, 7, 8, 11, 12, 13, 16, 17, 21, 22, 25, 26, 27, 30

15

July 2027

1, 5, 6, 9, 10, 11, 14, 15, 19, 20, 23, 24, 25, 28, 29

15

August 2027

2, 3, 6, 7, 8, 11, 12, 16, 17, 20, 21, 22, 25, 26, 30, 31

16

September 2027

3, 4, 5, 8, 9, 13, 14, 17, 18, 19, 22, 23, 27, 28

14

October 2027

1, 2, 3, 6, 7, 11, 12, 15, 16, 17, 20, 21, 25, 26, 29, 30, 31

17

November 2027

3, 4, 8, 9, 12, 13, 14, 17, 18, 22, 23, 26, 27, 28

14

December 2027

1, 2, 6, 7, 10, 11, 12, 15, 16, 20, 21, 24, 25, 26, 29, 30

16

To make your own 2-2-3 calendar or template, pick a Monday as day 1 and number the days from there. Crew A works on days 1, 2, 5, 6, 7, 10 and 11 of every 14, crew B on days 3, 4, 8, 9, 12, 13 and 14, and day 15 is day 1 again. In a spreadsheet one formula per cell does it: the day number is the remainder of the date minus the start date, divided by 14, plus one. The 2-2-3 schedule template for Excel has the 14-day cycle set up for four crews, with overtime counted per FLSA workweek. Holidays such as Christmas Day simply fall on whichever crew is on that date, which in this calendar means crew A works 25 December in both 2026 and 2027, so many teams agree a swap for those dates in advance.

How many days a month you work on a 2-2-3 schedule

Working days on a 2-2-3 schedule come to 14 to 17 a month, around 15 on average. The number moves because months are not a multiple of 14 days: February always has 14, and a 31-day month that starts and ends on working days can reach 17, as May 2026 and October 2027 do for crew A.

Over a year the pattern evens out at 7 days in 14, so a crew works 182 or 183 days. In 2026 crew A works 183 days and crew B 182; in 2027 it is the other way round. On 12-hour shifts that is roughly 2,190 hours a year, and each crew works 26 of the 52 weekends.

Hours on 8, 10 and 12-hour shifts

The 2-2-3 cycle fixes the days; the shift length decides the hours. Because one week of the fortnight holds more shifts than the other, the weekly hours are never the same two weeks running:

Shift length

Hours per 14 days

Average per week

Heaviest and lightest week

12 hours

84

42

60 and 24, or 48 and 36

10 hours

70

35

50 and 20, or 40 and 30

8 hours

56

28

40 and 16, or 32 and 24

Which pair applies depends on the day the week is counted from, and that is exactly what decides overtime in the US. On 8-hour shifts the 2-2-3 becomes a part-time pattern of 28 hours a week. Headcount follows from the average: one post on one 12-hour shift seven days a week needs two people, around the clock it needs four, and covering 24 hours with three 8-hour shifts on a 2-2-3 takes six crews, each averaging 28 hours.

Overtime on a 2-2-3 schedule in the US

The Fair Labor Standards Act requires employers to pay non-exempt employees time and a half for every hour over 40 in a workweek, and the Department of Labor is explicit that hours may not be averaged over two or more weeks. So a 2-2-3 crew on 12-hour shifts that averages 42 hours still earns overtime in some weeks, and how much depends on where the workweek starts.

Under 29 CFR 778.105 a workweek is a fixed, recurring period of 168 hours that may begin on any day and at any hour. Different groups of employees may have different workweeks, but once a start has been set it stays: it may only be changed for good, and not to avoid overtime. With the cycle starting on a Monday, as in the crew table:

Workweek starts on

12-hour shifts: overtime per fortnight

10-hour shifts: overtime per fortnight

Monday or Friday

20 hours (60 and 24)

10 hours (50 and 20)

Tuesday, Wednesday, Thursday, Saturday or Sunday

8 hours (48 and 36)

none (40 and 30)

Over a year of 26 fortnights, the 12-hour difference is 520 against 208 overtime hours per employee. On 8-hour shifts no week goes over 40 hours, wherever it starts. Crew B, seven days behind, gets the same split in the opposite order, so one workweek gives both crews the same total.

Consider a distribution centre that picks orders from 06:00 to 18:00 every day of the week and needs ten pickers on the floor. On a 2-2-3 with two crews of ten, a workweek that starts on Monday produces 400 overtime hours every fortnight across the 20 pickers. The same rota with a workweek starting on Wednesday produces 160. Nobody works a different day; only the payroll calendar changed, and it has to be settled before the first cycle runs.

State law can add a daily rule. In California, non-exempt employees are paid time and a half for hours over 8 up to 12 in a workday and double time above 12, according to the state's Labor Commissioner, unless the employer has adopted an alternative workweek schedule under the state's rules. On a 12-hour 2-2-3 that makes 4 hours of every shift overtime, 28 hours per fortnight, whichever day the workweek starts. The seventh-consecutive-day rule never applies, because a 2-2-3 has at most three working days in a row.

Is a 2-2-3 schedule good?

For employees, the strongest points are the three-day weekend every other week and the short runs: nobody works more than three days in a row, and half the days of the year are free. The cost is the 12-hour shift itself and the heavy week, when 60 hours fall into seven days. Childcare is harder to arrange on a pattern that changes from week to week, and people who commute far feel every long shift.

For employers, a 2-2-3 makes cover predictable: one crew always relieves the same other crew, there are two handovers a day at most, and a crew knows months ahead which days it works. It fits work with flat demand. A business with a busy Saturday and a quiet Tuesday puts the same headcount on both, so peaks need extra shifts on top. Each absence also leaves a full 12-hour shift to cover, usually with overtime, and a shift swap between crews can stretch a three-day run into four. Among the other shift patterns for 24/7 cover, the DuPont schedule trades the every-other-weekend rhythm for a four-week cycle with one seven-day break.

In the UK the same cycle is mostly called the Panama shift pattern, and the rules around it are different. UK law sets limits on working time and rest rather than an overtime premium: employers do not have to pay for overtime at all, as long as average pay for all hours worked stays above the National Minimum Wage, according to GOV.UK. The Panama page covers the pattern from the UK side.

Keeping a 2-2-3 rota on track in Shiftbase

In Shiftbase employee scheduling, the 12-hour shift is saved once as a shift template with its start, end and break, and each crew can be a team in the schedule. While planning the first fortnight, the planner sees availability, contract hours and approved leave next to every gap, and fills it automatically or by hand. Employees see their days in the mobile app. Clocked hours from time tracking show what each person actually worked per week, including held-over shifts, which is what overtime is worked out from. With absence management, a sick report or approved leave appears in the same schedule, so an uncovered shift on day 9 is visible before it starts.

Frequently asked questions

The 2-2-3 schedule uses the same 14-day cycle as the Pitman schedule and the Panama shift pattern: 2 days on, 2 off, 3 on, 2 off, 2 on and 3 off. The names are used loosely, and in the US 2-2-3 and Pitman often mean the same rota. Where people draw a line, the Pitman schedule more often means fixed day and night crews and Panama crews that rotate between them.

Weekly hours on a 2-2-3 schedule average 42 on 12-hour shifts, 35 on 10-hour shifts and 28 on 8-hour shifts. The weeks are uneven: on 12-hour shifts a crew works 60 hours one week and 24 the next, or 48 and 36, depending on the day the week is counted from.

On a 2-2-3 schedule an employee works 14 to 17 days a month, around 15 on average, and 182 or 183 days a year. February always has exactly 14 working days, while a 31-day month can have up to 17.

A non-exempt employee on a 12-hour 2-2-3 schedule in the US gets 8 or 20 hours of overtime every two weeks under the FLSA, depending on the day the workweek starts. On 10-hour shifts it is 10 hours or none, and on 8-hour shifts none. In California, daily overtime adds up to 4 hours on every 12-hour shift, 28 hours per fortnight, unless an alternative workweek schedule has been adopted.

Staffing a 2-2-3 schedule takes two employees for every post that runs one 12-hour shift seven days a week, and four for a post staffed around the clock. Covering 24 hours with three 8-hour shifts takes six crews. Cover for leave and sickness comes on top of those numbers.

A 2-2-3 schedule calendar starts from one fixed date: pick a Monday as day 1 and count the days from there. Crew A works days 1, 2, 5, 6, 7, 10 and 11 of every 14, crew B works days 3, 4, 8, 9, 12, 13 and 14, and the pattern repeats from day 15. The same rule works in a paper calendar, a spreadsheet template or scheduling software.

Employees who want long weekends and short runs of work tend to like a 2-2-3 schedule: every other weekend is three days off and nobody works more than three days in a row. It is harder on people with fixed childcare or long commutes, because the 12-hour shifts and the 60-hour week in each fortnight leave little room on working days.

Rinaily Bonifacio
Rinaily BonifacioSenior Content Marketer

Rinaily writes for Shiftbase about HR, scheduling and building teams people actually want to work in. She turns the messy reality of workforce planning into practical advice you can put to work today.

See all terms